Company & Project

Company Offering Hauling Project: CONVEYABULL, INC

Project Name: Floy Mill tailings to Moab/Green River

Hauling Rates & Pay Terms

Tractor Trailer Belly Dumps: $141 per hour

Payment Terms: Weekly Pay

100% of the hourly rate paid by direct deposit every Friday following the week that work was performed. i.e. Work Monday 10/3/22 through Sunday 10/9/22 shall be paid by Friday 10/14/22.

Materials & Quantities

Tractor Trailer Belly Dumps Needed: 8


Mill tailings: 13,000 tons

Project & Source Locations

Project Location

Floy Mill tailings to Moab/Green River
38.917282, -109.937347


Sources

Neilson construction Moab, UT
38.4686785, -109.4432567
FH94 FM, Spanish Valley, UT 84532, USA
Route to Project

Loading & Delivery Hours

Project Delivery Hours
Opens at 6:00 AM
Closes at 6:00 PM

Neilson construction Moab, UT
Opens at 6:10 AM
Closes at 6:00 PM

Project Schedule

Hauling Days: Monday - Friday

Hauling Start Date Est: 10/23/2023

Hauling Completion Date Est: 11/10/2023

Other Info

Additional Notes:
💵$141 per hour for Double Belly Dumps

💵$120 per hour for Single Belly Dumps (min legal payload of 28 tons)

🪨The first 4,000 tons will go to the Moab pit. The remaining 9,000 tons will go to the Nielson Construction Green River pit https://maps.app.goo.gl/1fn3oNrVUqy6DVif8

Brokers are prohibited.

This project is complete. Its last day of hauling was 2023-11-10