Company Offering Hauling Project: CONVEYABULL, INC
Project Name: NY State Transmission Line - AREA 1 CHPE (16723 NY-22, Putnam Station, NY 12861, )
Tractor Trailer End Dumps: $150 per hour
Dump Trucks: $125 per hour
Payment Terms: Weekly Pay
100% of the hourly rate paid by direct deposit every 3rd Friday following the week that work was performed. i.e. Work Monday 3/4/24 through Sunday 3/10/24 shall be paid by Friday 3/29/24.
Tractor Trailer End Dumps Needed: 80
Dump Trucks Needed: 100
Contaminated Soil: 30,000 tons
Clean Excavated Dirt: 31,000 tons
Project Location
NY State Transmission Line - AREA 1 CHPE
43.7391119, -73.4059809
16723 NY-22, Putnam Station, NY 12861,
Sources
Waste Management - Green Ridge
43.1864693, -73.614747
424 Peters Rd, Gansevoort, NY 12831, USA
Route to Project
Dresden Dump Location
43.67312831309795, -73.41173050791286
Route to Project
Project Delivery Hours
Opens at 7:00 AM
Closes at 5:30 PM
Waste Management - Green Ridge
Opens at 7:00 AM
Closes at 3:30 PM
Dresden Dump Location
Opens at 7:30 AM
Closes at 4:30 PM
Hauling Days: Monday - Friday with occasional Saturdays
Hauling Start Date Est: 10/25/2023
Hauling Completion Date Est: 04/30/2025
Additional Notes:
This is a 2 year project. AREA 1: segments 1 and 2. Putnam, NY to Whitehall, NY - 17 miles. Map link (see blue segments): https://tinyurl.com/chpearea2
💵Tractor Trailer End Dumps: Mon-Friday Rate: $150/hr. SATURDAY RATE: $175/hr.
💵Tandem and Triaxle Dump Trucks: Mon-Friday Rate: $125/hr. SATURDAY RATE: $150/hr.
Hauling out trench excavated dirt from KIEWIT's New York State (CHPE) Transmission Line project.
Tractor Trailer End Dumps must be full framed trailers.
Prevailing Wages do NOT apply.
Heavy Haulers 20 ton - 45 ton : Mon-Friday Rate: $150/hr. SATURDAY RATE: $175/hr.
Brokers are prohibited.
If you want to haul on this project, click the Reserve Trucks button below.