Company & Project

Project Contractor: KNIFE RIVER

Project Name: Heart Butte Bike Path (MT)

Hauling Rates & Pay Terms

Dump Trucks: $151.03 per hour

Side Dumps: $171.68 per hour

Belly Dumps: $171.68 per hour

Payment Terms: Weekly Pay

100% of the rate paid by direct deposit every 2nd Friday following the week that work was performed. i.e. Work Monday 6/1/26 through Sunday 6/7/26 shall be paid by Friday 6/19/26.

Materials & Quantities

Dump Trucks Needed: 7

Side Dumps Needed: 7

Belly Dumps Needed: 7


Pit Run: 2,700 tons

Haul Off Dirt: 2,700 tons

Project & Source Locations

Project Location

Heart Butte Bike Path (MT)
48.282204, -112.835656


Sources

Schellinger Valier Pit
48.31364905049875, -112.51682010311391

Route to Project

Loading & Delivery Hours

Project Delivery Hours
Opens at 7:00 AM
Closes at 5:00 PM

Schellinger Valier Pit
Opens at 7:00 AM
Closes at 5:00 PM

Project Schedule

Hauling Days: Monday - Friday with occasional Saturdays

Hauling Start Date Est: 06/29/2026

Hauling Completion Date Est: 07/17/2026

Other Info

Additional Notes:
Must be full size dump trucks - tandem axle or more.

The stated Dump Truck rate of $151.03 per hour includes a 7.5% fuel surcharge.

The stated Side Dump & Belly Dump (single trailer) rate of $171.68 per hour includes a 7.5% fuel surcharge.

Fuel Surcharge Terms: Base fuel price is $3.85 per gallon (MG revised 7/8/26 to reconcile with advertised values above). For every 10 cents above this price, the fuel surcharge increases rates 1%. See EIA Rocky Mountain (PADD 4) Diesel Fuel Index linked here: https://www.eia.gov/dnav/pet/pet_pri_gnd_dcus_r40_w.htm

Brokers are prohibited.

This project is complete. Its last day of hauling was 2026-07-17